Thursday, 28 February 2019

Building Diamond Pt 2



I the last blog I showed how the building was built and hinted at the work which was happening in R79. In this blog I will show you the work that went into building the machine itself. To start with R79 had to be filled with the infrastructure that we were going to use on building it. That meant ordering up tools, benches, fixtures, jigs, cleaning equipment and lifting equipment plus a whole lot more.







So where do you start, and empty building needed filling with equipment




The tripod was part of the survey equipment they world need to mark out where some of the heavy stuff was going, the benches were supposed to be for use but no use to when we were doing. The are still around over in the main building and used there










We had a kitchen but no tables yet




An office, not that I used it




Another office which I ended up in




And a place to store equipment







Within days of the place being given over for use equipment started coming in












More parts came in 





That made up the two ovens you see either side of the build trolley that had been delivered




The manager trying out the tug you saw in an early photo















The trolley was placed in the clean room





 and the plates fitted for the assembly of the vacuum string









Test equipment came in like the pump cart you see in the centre along with leak detectors. We ended up with thirty pumping carts, they cost 20k each and over 16 leak detectors at around 14k each and this was for only the first stage of building the machine






The ovens ended up looking like this with a lifting frame around it
















While this was going on my job was being over in the main building taking charge of these which were being delivered from Germany. They are what we called ID makeups



Th ID stands for Insertion Device, it was something that would go between  sections of the storage ring. These were late in coming so this section would be going in so we could run









They were put in storage tents to keep clean because the building was still a dusty construction site. I had to make sure that they still held a vacuum and fix a small pump controller to it so the ION pumps could run. I had to check the pressures twice a day & write the readings. It only took around twenty minuets with the first ones but by the time we had all of them I was spending a couple of hours checking them




We also took delivery of this second hand container to store equipment and tools. Eventually this container was moved outside and only replaced with a new one last year




It looks a little space to start with only having a couple tool boxes in it and a few parts on the shelves. We had eight tool boxes that cost the best part of 20K when fully stocked








This was another thing I sourced, a Lamina Flow Tent, the idea was to blow clean air though it and over the equipment we were assembling keeping it clean. By the time we finished we has seven of them and six smaller ones. I took ages working out the size to go through the labyrinth, after they were ordered I was about to go in through one of the labyrinths and noticed they had fitted pipes along both sides of the walls, I was not best please finding this out. The cabinets had to be quickly modified so I could get them in.







In R79 the first of the storage ring vessels were arriving on wooden boxes from Germany












The vacuum  strings were loaded up onto the build trolley




The ion pumps fitted





and strapped in place

















till they were all in place










While they were assembling the vacuum strings it was quite busy with technicians putting parts on





Now though I was involved it some of the work you have seen I was also keeping an eye on the engineering side for the Vacuum Group and as I was looking after the lifting equipment I was making sure it was up to the job. The first of the girders came in that the vacuum strings would be fitted to









One of the first thing to do was load test one with the correct weights and then take it to the storage ring on a dummy run





It was loaded on a trailer and transported to the Diamond building along the roads in Rutherford.





Then onto the Diamond construction site






The into the building where it was unloaded








Lifted on the crane and transported around the top of the storage ring





across the bridge being built





The finally into the storage ring





where It was lowered into place with quite a crowd watching







as we all thought it went off without a problem













You may think why go to all this effort if it was that easy. We had built a replica of the cable trays that were going to be part of the problem in the storage ring  over in R79 this showed what we would encounter putting in the fully assembled girders. The test over on the Left here does not have them







Then there was the amount of clearance from the walls to the lifting brackets and frames to contend with





It all ran very close to the ratchet wall




and even closer to the light fittings on the wall. When the real thing went in it would have valves gauges and other items protruding which if damaged could cause thousands of pounds worth of damage







 
The last thing they had to contend with was lining up the bearing serface with the cam which you can see in the photo above. There  are four and one person watches it was it comes into contact makeing sure it lands correctly







Over in R79 the first string was ready for the oven  and had to be transferred out of the clean room to be lifted in







This was quite a process as a lifting from had to be lowered onto the string













It was quite an operation which took a lot of people to make sure it all came down correctly in place








 







Once this was done tie rods were connected to lifting points on the string




and the whole thing was lifted in the air 







and over into the oven






where it was lowered back down in place to be baked out










The String was baked under vacuum to get the optimum vacuum which is around 10x10-10 mbar it was baked in the over for around 72 hours and controlled by computer over this time




then around a week later when it had cooled down the process of lifting it out  happened again, only this time it was transferred to the girder.







But first we had a dummy run







to check it all fitted on the supports






this was no easy task as it had to be done with great accuracy to check for any problems















The next time we did this it was for real and the magnets would be in place














This would complicate things  because of the clearance








but they were split so it was a little easier














First the finished string was brought through the workshop



to be lowered onto the girder with all the magnets in place




again people watched as it was lowered  in place to ensure nothing snagged on the way down and cause damage




it was watched every inch of the way down






till it was finally in place
When it was finished it looked like this, all 14 odd tons of it now all that was left was to build 71 more. The green magnet you see was fitted last and slid sideways into place.
In the next blog I will show you how they were lifted in place over in the storage ring the connected up along with the other work that was done to make the machine work